Replaced Upper Gear Leg Intersection Fairing Flange

The upper gear leg intersection fairing has a split in it to allow it to be flexed open and slipped over the gear leg. Once installed, a screw holds the split closed. Originally, there was a piece of fiberglass glued here with a small wood screw holding the joint closed. After repeated installation, the screw loosened up so I decided to replace it with a piece of aluminum and a nutplate. Now I can use a machine screw and there is positive locking of the screw with the nutplate. An added bonus is that the piece of aluminum forces the joint into alignment.

Here’s the other side of the joint with a torx machine screw and a countersunk washer.